Feb 11- Feb 15
Jump to navigation
Jump to search
Feb 14th- After the weekly meeting Ann Marie and I replaced the covers of the lights in the clean room with UV filtering covers. We soon realized that the length of two lights were shorter than the other four. Brendan cut the UV plastic tubes and I then assisted Ann Marie install the new covers.
Feb 15th- Ann Marie and I were going to clean the tank today, but as I arrived, Ann Marie was discovering that a reaction was occurring when the tank was cleaned with the chemical we were using, so we did not clean the tank.