Carl's Weekly Goals

9/12/07 - 9/19/07

  • test polishing techniques on the square fibers
  • Test BC-600 epoxy and compare to 20-3238
  • research electroplating to coat the scintillators and waveguides
  • continue to post my results on the wiki

Matt's Weekly Goals

9/19/07 - 9/26/07

<td0>
TASK STATUS
research various methods of fringe pattern analysis in progress
post findings on the wiki in progress
begin running parSA tests on the cluster cluster is able to run
formulate a plan to determine the best parSA scheduler for the project plan in process of being formalized
  • research various methods of fringe pattern analysis
  • post findings on the wiki
  • begin running parSA tests on the cluster
  • formulate a plan to determine the best parSA scheduler for the project